Compressor Commissioning Checklist

https://eauditor.app/
Compressor Commissioning Checklist
Section 1: Check Before Start-up
1. 1. Have you read and understood all the manuals (compressor, UniSAB, chiller, etc.)?
Yes
No
N/A
2. 2. Have you read and understood the manuals for third-party components (electric motors, valves, etc.)?
Yes
No
N/A
3. 3. Is the unit installation and vibration damper adjustment correct?
Yes
No
N/A
4. 4. Have you carried out functional testing of the safety equipment?
Yes
No
N/A
5. 5. Are the opening pressures on all safety valves correct?
Yes
No
N/A
6. 6. Have you conducted a vacuum test?
Yes
No
N/A
7. 7. Is the UniSAB setup correct (refer to the list of settings)? 
Yes
No
N/A
8. 8. Have you checked the VSD set-up, if applicable?
Yes
No
N/A
9. 9. Is the oil level within the required range?
Yes
No
N/A
10. 10. Has the heating element in the oil been on for 6-8 hours before startup?
Yes
No
N/A
11. 11. Have you taken a sample of the primary refrigerant, and is it free from water, air, etc.?
Yes
No
N/A
12. 12. Is the motor rotation direction correct?
Yes
No
N/A
13. 13. Is the coupling properly aligned?
Yes
No
N/A
14. 14. Is the compressor cooling connected correctly?
Yes
No
N/A
15. 15. Is the plant free from leaks?
Yes
No
N/A
16. 16. Are the valves in the correct position for operation?
Yes
No
N/A
Section 2: Check After Start-up
1. 1. Is the capacity regulation system working correctly?
Yes
No
N/A
2. 2. Is the refrigerant charge adequate at full load?
Yes
No
N/A
3. 3. Have you checked the unit for vibrations?
Yes
No
N/A
4. 4. Have you checked the unit for vibrations (for variable speed)?
Yes
No
N/A
5. 5. Have you made a startup log at full load (on the back of this form)?
Yes
No
N/A
6. 6. Have you taken a representative lubricating oil sample after about 1 hour of operation, and will you save it for a minimum of 1 year from the commissioning date?
Yes
No
N/A