Pre-Startup Safety Review(PSSR) Checklist

https://eauditor.app/
Pre-Startup Safety Review(PSSR) Checklist
Section 1: Pre-Startup Safety Review(PSSR) Checklist
1. 1. Have all pinch points and points of operation been properly guarded?
Yes
No
N/A
2. 2. Have all chains and sprockets been properly guarded?
Yes
No
N/A
3. 3. Are there any exposed set screws, key ways, collars, etc?
Yes
No
N/A
4. 4. Have all pulleys and belts been properly guarded?
Yes
No
N/A
5. 5. Have augers (if present) been properly guarded?
Yes
No
N/A
6. 6. Are all machine guards securely attached?
Yes
No
N/A
7. 7. Are interlocks prohibited from being bypassed if applicable?
Yes
No
N/A
8. 8. Test all interlocks to ensure functioning properly if applicable?
Yes
No
N/A
9. 9. For saw blades, is only the length necessary to cut product exposed?
Yes
No
N/A
10. 10. Are all shafts ends covered with a non-rotating cap or cut down to a length of less than 1/2 the diameter of the shaft?
Yes
No
N/A
11. 11. Is the machine wired according to code? (National Electric Code, National Fire Protection Association)
Yes
No
N/A
12. 12. Is the machine grounded?
Yes
No
N/A
13. 13. Is the power supply correctly fused and protected?
Yes
No
N/A
14. 14. Will additions or modifications require an Arc Flash analysis?
Yes
No
N/A
15. 15. Are all electrical connections secured, cords only the length necessary, conduit only used where required (no cords running through walls, under doors, etc)?
Yes
No
N/A